A:When drilling starts working,reaming sleeve will open,borehole range will increase,which will casing shoe and casing tube. |
B:When finish drilling in overburden layer,pay attention to reverse circulation,reaming sleeve circles up,eccentric drilling bit lifts out from the borehole. |
C:The casing that can be left in the borehole to prevent borehole from collapsing while pulling out pipe and grouting concrete. |
D:Regular drilling bits can be applied to drill the depth as required in the rock stratum. |
model | casing tube O.D./mm | Maximum O.D. of guide device/mm | bit diameter/mm | casing shoe I.D./mm | maximum reaming O.D./mm | hammer style |
108 | 108 | 92 | 84 | 86 | 118 | 3" |
114 | 114 | 100 | 92 | 94 | 124 | 3" |
127 | 127 | 110 | 100 | 102 | 136 | 3-4" |
146 | 146 | 124 | 115 | 117 | 156 | 4" |
168 | 168 | 146 | 134 | 138 | 178 | 5" |
178 | 178 | 156 | 144 | 148 | 193 | 5" |
183 | 183 | 160 | 144 | 152 | 193 | 5" |
194 | 194 | 178 | 165 | 167 | 208 | 6" |
219 | 219 | 203 | 189 | 193 | 237 | 6-7" |
245 | 245 | 220 | 206 | 210 | 260 | 6-8" |
273 | 273 | 256 | 238 | 242 | 308 | 8" |
325 | 325 | 297 | 280 | 285 | 355 | 8-10" |
377 | 377 | 351 | 328 | 333 | 420 | 10-12" |